Crossbridge, Turn Around

Crossbridge, Turn Around
  
Introduction
In June 2021 SubC was awarded the mechanical scope of the planned Turnaround on Crossbridge Energy Refinery in Fredericia. We have spent 3 months on the planning and preparation to ensure a safe and well-planned Turnaround.
 
In a turnaround, the plant (or part of the process) is taken out of production for the purpose of inspecting and maintaining or exchanging process equipment.
 
SubC’s scope of work
SubCs scope was the mechanical scope which also was the main scope of the TA, the scope consisted of:
·  Isolating components
·  Disassembling the equipment
·  Assembling, repairing of welding
·  Pressure testing
 
In addition to the site works, SubC’s project team took part in the project management, planning and preparation in cooperation with the management team of the refinery TA-team.
 
Preparation phase included
·  Ensuring a safe working environment
·  Management of personnel, tools, and supervision
·  Preparation of work packages
·  Reporting
 
Safety, quality, and delivery
During the campaign, which was intensively for 2 weeks, we were praised for our led safety culture as well as keeping our workspace nice and tidy. The campaign was executed without any recordable incidents and on time.
 
Second phase of the scope is to be initiated spring 2022, where the campaign is to be completed.
 
We thank our employees for a successful TA and for a job well done. Even in the most hectic hours, you kept on going and kept the spirit high.